Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

Could I get help with this ?
how many different types of ventilation are commonly used in the welding shop?
How do I solve 8k-9(4K+4)
Four students write a description of the cell membrane. Student 1: The cell membrane controls reproduction and is found only in plant cells, Student 2: The cell
What is the relationship between species richness - the number of species in an ecosystem - and ecosystem services? A. Species richness and ecosystem services a
HELPPP ITS DUE 22:00/10pm
When a person loses contact with reality and experiences irrational ideas and disordered perceptions, they are experiencing:_____________
Can anyone help I’m struggling with this
If ZC and ZD are supplementary and mZC = 67°, find mZD
Need help with this math problem ASAP. Look at the picture attached. The linear function f(x) passes through the points (0,3) and (2,7). A few values from the e