A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Two 4.0kg masses are 1.0m apart on a frictionless table. Each has 1.0μC of charge. Part A What is the magnitude of the electric force on one of the masses? What
what is the historical circumstance for the third amendment?
Each leg of a 45-45-90 triangle has a length of 6 units. What is the length of its hypotenuse?
Explain why an addition problem that has a 4-digit addends could have a 5 digit sum.
Another word for acadians
Which pair of molecules both contain carbon atoms?
In which form of government do delegates speak on behalf of citizens? popular sovereignty authoritarian monarchy representative totalitarian
why is pi the best example of an exponent
Who is W. E. B. Du Bois?
You are working at establishing a computer network and communications support for incident personnel. Where are you working? a. Operations Section b. Planning S