Comparing a static planning budget to actual costs is not a good way to assess whether variable costs are under control. T/F

Respuesta :

Nyctalus
Nyctalus Nyctalus
  • 11-09-2019

Answer: False

Explanation: Static budget refers to that budget which is made for the upcoming period. A static budget incorporates anticipated values of inputs and outputs in it. It does sometimes assumes extreme business environment conditions.

Therefore, it is not feasible to compare the actual budget with the static plan as there is a high chance that both will differ by a high amount.

Hence, the given statement is false.

Answer Link

Otras preguntas

How is preimplantation genetic diagnosis used in the future? Please help Thank you
25 Points!! What is the volume of the prism 1 1/2ft 3 1/2ft 2 1/2 ft? Please answer when you have the time to.
Give an example of a well-stated research question that involves estimating a characteristic about the population of part-time students at your college. Improve
The question is in the attachment.
Should Puerto Rico become a U.S. state?
ILL GIVE THE BRAINLIEST TO THE PERSON WHO DOES THIS FOR ME THANK YOU (Statistics hw)
What does the light independent reaction make? (Multiple Choice) Water Carbon dioxide Sugar Light energy
pt 2 to my last question
ploring Comparative Elements vement of the progress bar may be uneven becouse ouestions con be worth more or less including zero) depending on your answer Read
How do I solve this problem? Also, shouldn't the answer be square root 61 because you do 5^2+6^2=c^2?